EREĞLİ IRON AND STEEL WORKS CO.
ERDEMİR PORT (ER-PORT)

Harbour Facilities
Harbour Facilities have started operating in 1964 for
marine delivery of raw materials like ore, coal, limestone,
etc. and transportation of products and they have been
expanded during II. Phase Expansion. There exist a 1,245
meters main breakwater and a 684 meters subsidiary
breakwater. slag and Ro-Ro quays are also present as well
as cast freight and general cargo services.
Old
harbour is suitable for 60,000 DWT capacity ships with 295
meter loading quay and 405 meter coal and ore unloading
quay. There are 3 cranes that have capacities of 1,000,
1,400 and 1,500 tons/hour on the unloading quay. On the
loading quay there are 4 loading and unloading cranes of
which one has a lifting capacity of 25 tons and the other
three having a lifting capacity of 15 tons each.
The new harbour facilities that are suitable for 150,000
DWT ships started operating in September 1998. It is the
largest harbour of west Black Sea. It provides
considerable savings in freight charges and serves to
third parties as well. It has a 350 meters unloading pier
in 20 meters water depth and a 200 meters loading and
unloading pier and necessary equipment enabling 70,000
tons of ships to berth. There are two unloading cranes
each having 1,500 tons/hour capacity, a conveyor line with
2,500 tons/hour ore unloading capacity and another
conveyor line with 1,500 tons/hour coal unloading capacity
on the unloading pier and on the loading - unloading dock
there are 2 cargo cranes with a capacity of 40 tons each.
In addition, a 3,320 horsepower and two 2,700 horsepower
schottels, a 800 horsepower classical tugboat, a 15,5
meters long schottel type Pilot Boat and 2 hawser boat
provide pilot services.
|
Company Profile | Port
Of Erdemir |
|