PETKİM Petrokimya Holding
A.Ş.
RECENT PROGRESS
OF PROJECTS
08/01/2007
Expansion of the Water Pretreatment Unit :
An agreement
with value 12.815.412 FF + 1.589.366 USD was
signed in 1999 with OTV (Fransa)-Hidro OTV
(Türkiye) consortium for engineering,
procurement and supervisory services. In
2001 all equipment and material were
received on site. AKFEN A.Ş. has been
awarded the contract for construction work
with 3.287.592.919.898.-TL value which was
enacted on July 8, 2002. Construction work
has been completed in October 2004. The unit
was started up in 2005.
|
Expansion of Ethylene Plant :
The basic
engineering of the project which will
increase ethylene production capacity from
400.000 tons/year to 520.000 tons/year, has
been performed by Stone & Webster (UK) which
was the original engineering designer of the
plant. For engineering, procurement and
construction phases, bidding was started on
a lumpsum turn-key basis. The tendering was
finalized leading to signing of the 82.200
thousand US Dollars contract with MES/GAMA
on August 8, 2002. The consortium has
performed detailed engineering and
procurement services as well as construction
work. In january 2005 the plant was shut-down
to carry out the last portion of
construction activities. In March 2005
precommissioning and commissioning started.
On 15th May, 2005 trial operations commenced.
Construction of Heavy Metal Removal System,
also part of the project, was contracted
separately to ÖNCÜ İNŞ. A.Ş. on December 30,
2003 with the amount of 356.623.340.000.-TL.
HMR System has also been commissioned. The
plant started trial production on 15th
May, 2005 . In the test-run conducted on 20th
August, 2005 target capacity was achieved.
|
LDPE Plant Revamp and Debottlenecking :
Upon project
completion the production capacity of the
plant will have been raised from 190.000
tons/years to 310.000 tons/year. On November
7, 2001 license agreement of € 9.000.000 was
signed with STAMICARBON BV (Holland) and
engineering-procurement agreement of €
47.000.000 was signed with TECHNIP (France).
Licensing firm completed and submitted the
process design package on June 23, 2001.
Detailed engineering and procurement work
has been completed. After tendering for the
construction job TOKAR A.Ş. has been awarded
the contract amounting to
10.313.076.645.000.-TL which was enacted on
September 2, 2002. Construction work was
completed in December 2004. After
commissioning completion trial operations
started on May 24 th, 2005.
|
Second Expansion of PP Plant :
The basic
engineering of this project which aims to
increase the production of polypropylene
from 80.000 tons/year to 144.000 tons/year,
has been performed by Mitsui Chemicals (Japan).
Engineering, procurement and supervisory
services contract with the amount of 19.700
thousand US Dollars has been awarded to
Mitsui Engineering Shipbuilding Co. Ltd. (Japan)
and the agreement was signed on August 8,
2002. The firm has completed the detailed
engineering work, as well as shipment of
equipment and materials in 2004. After
bidding for construction work a contract was
signed with EMTA İnşaat on September 8th,
2004. Construction was completed in
September 2005. Recently commissioning is
under progress. After commissioning target
production capacity was attained.
|
Rehabilitation of Cooling Water System:
Foreign
engineering, procurement and supervisory
services contract of € 6.811.900 has been
awarded to SALINE WATER SPECIALIST (Italy)
on June 26, 2002. The firm has completed
engineering work and shipment of equipment
and materials. On April 9, 2003 the contract
with the amount of 4.176.182.266.250.- TL.
for construction of the new Cooling Towers G
and H has been signed with ALKE İNŞ. SAN. VE
TİC. A.Ş.- MARSİS İNŞ. A.Ş. Joint Venture.
Cooling Tower G reached mechanical
completion in December 2004. Concurrently
with the completion of Cooling Tower H the
project as a whole became operative in April
2005.
|
Rehabilitation of Demineralized Water Unit :
Engineering,
procurement and supervisory services
contract of € 2.946.560 was signed with OTV
(France) on April 10, 2002. The firm has
completed engineering work and shipment of
equipment and materials in 2003. In 2004,
bidding for the construction job was started.
Construction contract awarded to MARSİS İNŞ.
A.Ş. was signed on July 8th, 2004.
Construction work was completed in July
2005. The unit is fully operative.
|
Debottlenecking of Steam Generation Unit :
Technical
feasibility study of this modification which
will enable boilers to utilize natural gas
in addition to fuel-oil were assigned to
MITSUBISHI (Japan) in 2000. Engineering,
procurement and supervisory services have
been opened to bidding in 2001. Contract
award stage has been reached in 2002.Bidding
procedure for engineering, procurement and
supervisory services of the other project
package namely the installation of the
Second Steam Production Unit has been
started in 2002. However, in 2003, during
re-evaluation of investment projects with
the aim to cut investment expenditures both
bidding procedures were cancelled. In
October 2004, a new bidding was opened for
lumpsum turnkey supply of detailed
engineering, equipment, materials and
construction work covering natural gas
conversion and rehabilitation of four
existing boilers, gas turbine generator and
heat recovery system. Contract of
53.019.325.-Euro plus 19.459.800.-Swiss
Francs was enacted with ANSALDO CALDAIE (Italy)
– TOKAR A.Ş. consortium on March 25th, 2005.
The consortium is performing detailed
engineering and equipment supply. The
project completion is planned for 2007.
|
Chlorine Alkali Plant - Rehabilitation of
Electrolyzer System :
Chlorine Alkali
Plant has produced chlorine using mercury
cell electrolysis technology until 1997.
After a two-staged investment, in 2000,
mercury cells were dismantled and membrane
cell technology was adopted in 42 membrane
cells. In the new technology, however, the
useful life of anodes and cathodes is
limited to 6 years, the renewal of these has
become necessary to maintain the production
of chlorine in this plant and production of
VCM and PVC in the Complex. The project also
comprises the installation of an additional
membrane cell to compensate for chlorine
shortages during project implementation. An
agreement was signed on 1st
August, 2006 with Chlorine Engineers
Corporation Ltd. ( Japan ) for supply of
anodes and meshes. Contract negotiations are
being held for other parts of the project
with the same firm.
|
|