ADMINISTRATION COMPANIES IN THE PORTFOLIO 2003 PRIVATIZATION PROGRAMME 1985-2002 IMPLEMENTATIONS PRIVATIZATION SOCIAL SUPPORT PROJECT TURKCE FOR ENGLISH PUBLICATIONS
Administration Portfolio Social Project Programme Implementations Announcements Puplications E-Mail Links Menu    

TURKISH PETROLEUM REFINERIES CORPORATION

 

Auxiliary Units at Yarımca

STEAM GENERATION UNIT

STEAM GENERATION UNIT

 

 

 Capacity

:

120 Tons/hour (40 tons/h x 3 BW)

 Licensor

:

BW.CE

 Engineering & Supply  Contractor

:

SIM. Chem. U.K.,Tümaş-TURKEY

 Construction Contractor

:

Foster-Wheeler, U.S.A.

 Start up Date

:

07.04.1969 BW Boiler, 27.06.1973 CE Boiler

 Expansion Date

:

1975-1986

 Capacity After Expansion

:

6 x 100 = 600 Tons/h

 XHS Production in 2000

:

1.147.691 Tons

 

AIR GENERATION UNIT

AIR GENERATION UNIT

 

 

 Capacity : 5.000 Nm3/h
 Licensor : CENTAC
 Engineering & Supply  Contractor : SIM. Chem. UK, Tümaş-TURKEY
 Construction Contractor : Foster-Wheeler, U.S.A.
 Start up Date : 15 May 1969
 Expansion Date : 1972-1973
 Capacity After Expansion : 29.000 Nm3/h
 Production in 2000 : 73.670.937 Nm3

 

NITROGEN GENERATION UNIT

NITROGEN GENERATION UNIT

 

 

 Capacity : 840 Nm3/h
 Licensor : W.C. HOLMES
 Engineering & Supply  Contractor : SIM. Chem. U.K., Tümaş-TURKEY
 Construction Contractor : Foster-Wheeler, U.S.A.
 Start up Date : 05 May 1969
 Expansion Date : 1973
 Capacity After Expansion : 1.260 Nm3/h
 Production in 2000 : 1.936.155 Nm3
 

Republic Of Turkey Prime Ministry Privatization Administration 2003